Selskapspresentasjon 6. mars 2016Planlagte aktiviteter og kostnader første halvår 2016 (frem til start PFS) Engebø:Activity
| Further description
| Cost estimate
| Resource classification | • Core drilling approx. 6,500 meters in the open pit zone, drill core analysis, geotechnical assessments • Resource modeling and estimations in accordance with the JORC Code 2012
| USD 1,4 million | Process testwork and optimisation | • Further process tests and optimization of flowsheet • Target: Increased rutile recovery and define cost-effective process solutions • Reduce or avoid flotation?
| USD 2.0 million
| Engineering and cost review
| • Pre-engineering • Updated estimates for Capex/Opex
| USD 0.5 million
| Supply of process water and hydropower | • Assessment of alternatives • Applications with supporting documentation
| USD 0.6 million | Technical advisor and PFS coordination | • Assessment of candidates ongoing
| USD 1.5 million
| Project management and overhead | • Lean project team; project leader and 2– 3 key persons • General corporate overhead
| USD 3.4 million
| Contingency | • Approximately 10%
| USD 0.9 million
| Total |
| USD 10.3 million |
|
|