3kv. 2015 interim rapport fre. 13 november: Engebø:- Various activities related to the upcoming pre-feasibility study are ongoing. This includes i.a. preparation of a drilling program to improve resource classification, processing tests and optimisation work, and activities related to supply of process water and power. Nordic Rutile will establish an office in Naustdal and gradually manage development activities, stakeholder contacts and other public relations from this office. Kvinnherad:
- Nordic Mining has dialogues with international companies with commercial interests in the quartz value chain. Keliber:
- Process optimisation test work is ongoing in cooperation with specialised technology partners. The test work includes mineral separation techniques including dense media separation and flotation. Outotec (Finland) Oy (“Outotec”) carries out test work related to the lithium carbonate process. This includes test production in larger autoclaves and production of battery grade lithium carbonate which will serve as samples for pre-marketing efforts. Outotec also provides input to the definition of the process parameters as well as design of equipment configuration and parameters for each process stage. Together with cost and capex estimations this will be input to the PFS. Presentasjonen finner du her.
|
|