Post by pling on Jan 19, 2016 18:30:54 GMT
Fra Keliber Oy presentation 20. mai 2015Financial highlights –Pre-Tax IRR of 26 %
Total Site Oprerating Cost: 68,7 EUR/tonn Net Smelter Return: 170,4 EUR/tonn malm Financing round I
Capital financing round I EUR 4 M (2012-2013) Financing round II and III
Capital financing rounds II and III EUR 2.4 M and EUR 3 – 4 M / Potential IPO (2014-2016) Financing round IV
Project funding EUR 80 – 100 M (2018) Increased mineral resources and process R&D
- Company ’s exploration drilling programs have resulted a 390 percent increase in Company’s JORC compliant mineral resources during 2013 – 2015
|
|